Residents of Omkoi v Expert Committee on EIA Consideration et al.

Summary:

On 4 April 2022, members of Kabeudin village, an Indigenous Karen community in Omkoi district, Chiang Mai province, Thailand, filed a lawsuit at the Chiang Mai Administrative Court against the Office of Natural Resources and Environmental Policy and Planning and the Expert Committee on Environmental Impact Assessment Consideration. The legal action aims to revoke the alleged flawed environmental impact assessment (EIA) associated with the Omkoi coal mine project by the 99 Thuwanon Company. Residents argue that the coal mine poses substantial risks to long-term health and livelihoods. The lawsuit specifically targets deficiencies in the original EIA, which was executed over ten years ago, lacked meaningful community participation, and contains errors and omissions. Thailand’s National Human Rights Commission (NHRC) reportedly identified human rights violations in the EIA in 2020, and recommended a plan revision. If the project proceeds, residents fear it will infringe upon their right to a healthy environment and life-sustaining resources like clean air and water. The lawsuit seeks a transparent and legally compliant new EIA in line with Thai law and international standards. On 23 September 2022, the Administrative Court issued an order for temporary protection, thereby suspending the activities of the coal mining project until a final judgment from the Court is delivered.

Claim:

The residents of Omkoi assert that the EIA for the Omkoi coal mine project, conducted by the 99 Thuwanon Company over a decade ago, is fundamentally flawed and poses a significant threat to the community’s long-term health and livelihoods. The lawsuit seeks the revocation of the alleged outdated EIA and the initiation of a new assessment process characterized by transparency and meaningful community participation. The claim emphasizes that the original EIA lacked adequate opportunities for local engagement, contained errors and omissions, and was previously identified by the NHRC for human rights violations. The residents contend that allowing the coal mine project to proceed would violate their right to a healthy environment and life-sustaining resources like clean air and water.

Links:

The case documents are accessible via Climate Case Chart: Click here.

Status of the case:

The case is currently pending before the Chiang Mai Administrative Court of Republic of Thailand.

Suggested citation:

Residents of Omkoi v Expert Committee on Environmental Impact Assessment Consideration and the Office of Natural Resources and Environmental Policy and Planning, Chiang Mai Administrative Court of Republic of Thailand, Black Case Sor. 1/2565 (4 April 2022).

Last updated:
15 January 2024.

Categories
Domestic court Fossil fuel extraction Indigenous peoples rights Indigenous peoples' rights Participation rights Right to a healthy environment Right to health South Korea

Kang et al. v KSURE and KEXIM

Summary:
In March 2022, four individuals, including one Korean national and three Australian nationals from the indigenous community of the Tiwi Islands, filed a complaint before the Seoul District Court. The complaint specifically targets two public Korean debtor corporations—Korea Trade Insurance Corporation and Korea Export Import Bank—by challenging their financial support for the Barossa gas field development project. This fossil gas reserve initiative, led by SK E&S Co., Ltd. (a South Korean conglomerate), Santos Ltd. (an Australian oil and gas corporation), and Jera Co. (Japan’s largest power company), is located off the coast of Australia’s Northern Territory, near the Tiwi Islands. The applicants oppose the project, highlighting potential irreversible environmental, legal, and financial risks. The plaintiffs argue that endorsing the Barossa Gas Project would violate their constitutional rights to health and a healthy living environment. They are seeking a preliminary injunction to prevent the defendants from supporting the project.

Claim:
The claim underscores the environmental risks associated with the Barossa Gas Project, projecting an annual emission of 15Mt of CO2 and potential harm to the marine ecosystem, including endangered sea turtles, and indigenous communities. Legal risks involve insufficient consultation with indigenous communities and a potential dispute over control of the gas field given its location within the Indonesian exclusive economic zone (EEZ). Financial risks are tied to the project’s inconsistency with climate goals, an anticipated decline in fossil gas demand, and underdeveloped carbon capture and storage technologies. The plaintiffs base their claim on constitutional environmental rights, Tiwi Islanders’ property rights, and the South Korean National Finance Act. They emphasise the deficiencies in the consultation and assessment processes for the proposed Barossa pipeline in a habitat protection zone near the Tiwi Islands. The central issue revolves around whether the Tiwi Islanders were adequately consulted and if environmental and climate impacts were sufficiently assessed for the Barossa project.

Links:
The complaint is accessible for download below (in the original Korean).

Status of the case:
Pending.

Suggested citation:
Kang et al. v. KSURE and KEXIM (South Korea, Seoul District Court), pending case filed on 23 March 2022.

Last updated:
12 December 2023.

Categories
2023 Colombia Domestic court Emissions reductions/mitigation Indigenous peoples rights Indigenous peoples' rights Just transition litigation Participation rights Right to culture Self-determination Uncategorized

Pirá Paraná Indigenous Council and Another v. Ministry of Environment and Others (Pirá Paraná Case)

Summary:

On July 15th, 2022, the Pirá Paraná Indigenous Council, in collaboration with the Association of Indigenous Traditional Authorities of the River Pirá Paraná, initiated a ‘tutela’ proceeding against private corporations and Colombian authorities. This expedited legal procedure is only available when regular mechanisms are deemed inadequate to ensure the protection of the plaintiffs’ rights. The legal action arises from concerns related to the Baka Rokarire project, particularly its carbon credit initiatives, within the Indigenous territory situated in the heart of the Amazon rainforest, located in the Vaupés region. The central issue at hand is the potential violation of Indigenous fundamental human rights, including self-determination, self-governance, and the preservation of cultural diversity and integrity. The claimants argue that the individual who represented the Indigenous community in the project lacked proper legitimacy, while public authorities allegedly failed to safeguard Indigenous rights throughout the project’s registration and development. Private companies are accused of neglecting human rights due diligence standards and deliberately excluding Indigenous authorities from the decision-making process.

Claim:

The plaintiffs argue that the Baka Rokarire project, especially its carbon credit initiatives, violate their fundamental human rights as Indigenous people. Importantly, the lawsuit filed by the Pirá Paraná community does not contest land ownership rights but instead focuses on preserving the integrity of the territory, which holds great cultural and ancestral significance for Indigenous populations. Their primary concern centers around the absence of genuine Indigenous representation in the project’s agreement. Furthermore, they accuse public authorities of failing to fulfill their responsibilities in safeguarding Indigenous rights during the project’s registration and execution. Private companies involved are accused of neglecting human rights due diligence standards and intentionally excluding Indigenous authorities from the project’s development. The main argument is that the potential negative impact on Indigenous rights justifies legal intervention.

Decision:

Initially, based on the subsidiarity of the tutela mechanism, the Judicial Court deemed the case inadmissible, citing that the plaintiffs could have pursued other available legal avenues. The court’s rationale was that the tutela mechanism was not the suitable course of action in this instance, as there was no clear evidence indicating the presence of irreparable damage in the case. The Administrative Tribunal upheld this decision. However, in April 2023, a significant development occurred when Colombia’s Constitutional Court took the unprecedented step of reviewing the case. This marks the first-ever evaluation of a case involving the voluntary carbon market, potentially setting a legal precedent that will delineate the boundaries of activities permitted within territories inhabited by Indigenous communities in carbon credit projects. The Constitutional Court’s review will also encompass an examination of whether the tutela mechanism is the appropriate means for challenging these projects, especially concerning Indigenous rights. This decision to review represents a noteworthy opportunity to provide clarity regarding Indigenous rights and cultural preservation within the context of carbon offset initiatives.

Links:

The case documents are accessible via Climate Case Chart: Click here.

Status of the case:

The case is currently pending before the Constitutional Court of Colombia.

Last updated:

05 October 2023.